What Is Direct Labor Rate Variance & How To Calculate It?

The above definition is built on the premise that you already understand direct labor, direct labor refers to the effort expended in the conversion of raw materials to finished forms. The actual amounts paid may include extra payments for shift differentials or overtime. For example, a rush order may marginal cost formula require the payment of overtime in order to meet an aggressive delivery date. Mary’s new hire isn’t doing as well as expected, but what if the opposite had happened? What if adding Jake to the team has speeded up the production process and now it was only taking .4 hours to produce a pair of shoes?

Would you prefer to work with a financial professional remotely or in-person?

If there is no difference between the standard rate and the actual rate, the outcome will be zero, and no variance exists. Usually, direct labor rate variance does not occur due to change in labor rates because they are normally pretty easy to predict. A common reason of unfavorable labor rate variance is an inappropriate/inefficient use of direct labor workers by production supervisors. In this case, the actual hours worked are 0.05 per box, the standard hours are 0.10 per box, and the standard rate per hour is $8.00. This is a favorable outcome because the actual hours worked were less than the standard hours expected.

Practice Question

However, employees actually worked 3,600 hours, for which they were paid an average of $13 per hour. Labor rate variance arises when labor is paid at a rate that differs from the standard wage rate. Labor efficiency variance arises when the actual hours worked vary from standard, resulting in a higher or lower standard time recorded for a given output.

How confident are you in your long term financial plan?

Another element this company and others must consider is a direct labor time variance. In the manufacturing example, some workers may have special skills that command a higher salary, while others could be unskilled and less expensive. In both cases, it’s important to calculate the total aggregate expense for all the workers directly involved, accounting for the variances in their pay, benefits, and taxes to ensure an accurate total cost.

Our Services

Our mission is to empower readers with the most factual and reliable financial information possible to help them make informed decisions for their individual needs. This team of experts helps Finance Strategists maintain the highest level of accuracy and professionalism possible. At Finance Strategists, we partner with financial experts to ensure the accuracy of our financial content.

Fundamentals of Direct Labor Variances

  1. Thus the 21,000 standard hours (SH) is 0.10 hours per unit × 210,000 units produced.
  2. The labor standard may not reflect recent changes in the rates paid to employees.
  3. Direct labor can be analyzed as a variance over time, across products, and in relation to other process, equipment, or operational changes.
  4. A favorable outcome means you used fewer hours than anticipated to make the actual number of production units.

They pay a set rate for a physical exam, no matter how long it takes. If the exam takes longer than expected, the doctor is not compensated for that extra time. Doctors know the standard and try to schedule accordingly so a variance does not exist. If anything, they try to produce a favorable variance by seeing more patients in a quicker time frame to maximize their compensation potential. In this question, the Bright Company has experienced a favorable labor rate variance of $45 because it has paid a lower hourly rate ($5.40) than the standard hourly rate ($5.50).

Idle Time Variance

In other words, when actual number of hours worked differ from the standard number of hours allowed to manufacture a certain number of units, labor efficiency variance occurs. For example, a company is looking to hire more staff to meet the expected cost of labor in a production facility. Hiring new staff means that they will also be able to push out more total hours worked, resulting in more product. However, the rate that the new staff must be hired at is higher than the actual rate currently paid to employees.

Managers can better address this situation if they have a breakdown of the variances between quantity and rate. Specifically, knowing the amount and direction of the difference for each can help them take targeted measures forimprovement. As mentioned earlier, the cause of one variance might influenceanother variance.

In this case, the actual hours worked per box are \(0.20\), the standard hours per box are \(0.10\), and the standard rate per hour is \(\$8.00\). In this case, the actual rate per hour is $9.50, the standard rate per hour is $8.00, and the actual hours worked per box are 0.10 hours. This is an unfavorable outcome because the actual rate per hour was more than the standard rate per hour.

The time it takes to make a pair of shoes has gone from .5 to .6 hours. Mary hopes it will  better as the team works together, but right now, she needs to reevaluate her labor budget and get the information to her boss. Figure 10.7 contains some possible explanations for the laborrate variance (left panel) and labor efficiency variance (rightpanel).

Next, we must determine the total labor costs of the employees working those hours. In the auditing example, one auditor could be a senior team member with a higher salary, payroll taxes, and benefit costs than the two junior members. Each team member’s costs should be calculated independently and then added together to get the correct total. Labor rate variance is the difference between the expected cost of labor and the actual cost of labor. This variance occurs because of differences in standard versus actual rates.

With either of these formulas, the actual rate per hour refers to the actual rate of pay for workers to create one unit of product. The standard rate per hour is the expected rate of pay for workers to create one unit of product. The actual hours worked are the actual number of hours worked to create one unit of product.

The labor standard may not reflect recent changes in the rates paid to employees. For example, the standard may not reflect the changes imposed by a new union contract. The most common causes of labor variances are changes in employee skills, supervision, production https://www.simple-accounting.org/ methods capabilities and tools. An example is when a highly paid worker performs a low-level task, which influences labor efficiency variance. Let’s say our accounting records show that the line workers put in a total of 2,325 hours during the month.

Total actual and standard direct labor costs are calculated by multiplying number of hours by rate, and the results are shown in the last row of the first two columns. To compute the direct labor quantity variance, subtract the standard cost of direct labor ($48,000) from the actual hours of direct labor at standard rate ($43,200). This math results in a favorable variance of $4,800, indicating that the company saves $4,800 in expenses because its employees work 400 fewer hours than expected. Like direct labor rate variance, this variance may be favorable or unfavorable.

Direct labor rates are the labor costs directly resulting in the production of a product or delivery of a service. These costs include wages, payroll taxes, insurance, retirement matches, and other benefit costs. Primarily, it reviews the differences between the expected costs of labor and the actual costs of labor. It can also aid the planning and development of new budgets and serve as a means of gaining information on company performance.